Pre-Applications are available for potential applicants. A potential applicant may submit a formal written request form along with a non-refundable fee of $300 for a pre-application report on a proposed project at a specific site. The EDC shall provide the pre-application data to the potential applicant within 20 business days after receipt of the completed pre-application report request form and payment of the $300 fee. The pre-application report produced by the EDC is non-binding and does not confer any rights; the potential applicant must file an application before it can interconnect with the EDC's system.
Download, print, complete, and mail this application.
Distributed Generation Level 1 ApplicationDownload, print, complete, and mail this application.
Distributed Generation Levels 2, 3, 4 ApplicationDownload, print, complete, and mail this application.
Distributed Generation >10 MVA ApplicationAmeren Illinois Net Metering Coordinator
6 Executive Dr – Mail Code 925
Collinsville, IL 62234